• > 17-12-2015 FAT for GIS for Pakistan Patrind Hydropower Project


    On Dec 8, 2015, our staff accompanied the owner, owner's engineer, contractor's engineer to Pinggao Group Co., Ltd., and organized GIS FAT for Pakistan Patrind Hydropower Plant. In the process, our staff coordinated Pinggao to test strictly accordance with IEC standard and fully meet the requirements of owner's engineer for test procedure and practice. After 10 days of intense work, GIS FAT to a successful conclusion on Dec 17, 2015.