• > 24-7-2017 Finished and passed all type test for GIS CT & PT in the KEMA laboratory


    On May 14, 2017, our personnel and Pinggao Group personnel went to the KEMA laboratory of Holland witness the type test of GIS CT & PT of Patrind hydropower project of Pakistan. During the test, our staff careful on work, dedicated, with good sense of responsibility (every day to the test room earlier than KEMA test engineer) ,cooperated with test engineer for test preparation, witness test, test equipment dismantle and reassemble, and supply test required drawings etc.. Pakistan NTDC witness engineers are very satisfied with our products after witnessing CT accuracy tests after short circuits. We completed and passed all type test items on July 24, 2017, and KEMA type test certificate will be obtained.

  • Take Picture with the Test Engineer of KEMA


  • Lightning Impulse test for GIS CT


  • Power Frequency Withstand Test and Partial Discharge Test before Short Circuit for GIS CT


  • Short Circuit Test for GIS CT


  • IP Test for Terminal for GIS PT


  • Temperature Rise Test for GIS VT


  • Preparation for Tightness Test for GIS VT

  • < BACK
Copyright ? So-Finder Power Engineering Co., Ltd. All Rights Reserved